[December 18, 2008][1.5 Hours] Plumbed and installed brake pedals
[December 19, 2008][2 Hours] Trimmed subpanel for vent interference, magetometer tray
[December 21, 2008][9.5 Hours] Installed tubing for electric fuel pump and filter; finished fuel line routing
[February 12, 2009][3 Hours] Started mounting the EFIS magnetomer support tray
[February 28, 2009][1.5 Hours] Mounted manifold pressure transducer; riveted magnetomer tray
[March 2, 2009][2 Hours] Mounted magnetometer
[August 18, 2009][2 Hours] Fixed interference with flap actuator channel
[September 1, 2009][1 Hour] Painted floors misc stuff
[September 3, 2009][2 Hours] Installed Floors
[September 4, 2009][2.5 Hours] Installed flap position sensor
[September 5, 2009][3 Hours] Stick grips / Flap motor wiring
[September 7, 2009][6 Hours] Painted bottom cowl, stick wiring, engine ground
[October 27, 2009][2 Hours] Bled the brakes
[November 13, 2009][3 Hours] Installing stuff in panel; pitot/static plumbing
[November 14, 2009][5 Hours] Power Point wired; sealed avionics tray; etc..
[November 15, 2009][4 Hours] Installed avionics, ELT wiring, painted map box
[November 16, 2009][1 Hour] Attempted to put passenger warning label on
[November 19, 2009][2 Hours] Installed map box and panel blanks
[November 20, 2009][1 Hour] Started annunicator lights
[November 22, 2009][3.5 Hours] Wired up annunicators, wrapping wires
[November 23, 2009][2.5 Hours] Tying off wires ; took off canopy
[November 29, 2009][3 Hours] Covered wires going up firewall, installed ELT. Installed controls
[November 30, 2009][3 Hours] Routed control cables, work on canopy fairing
[December 1, 2009][1.5 Hours] Canopy fairing
[December 2, 2009][4.5 Hours] Canopy fairing heater FAB other stuff
[December 3, 2009][0.5 Hours] Canopy fairing
[December 9, 2009][2.5 Hours] Canopy fairing, control cable passthrough
[December 10, 2009][0.5 Hours] Canopy Fairing
[December 11, 2009][2 Hours] Finished main canopy fairing; pinhole filing
[December 13, 2009][4 Hours] More canopy fairing, blast tube, rear window
[December 14, 2009][1.5 Hours] test fit canopy
[December 18, 2009][2 Hours] Canopy prep
[December 19, 2009][6 Hours] Primed canopy fairing, painted rollbar
[December 21, 2009][1.5 Hours] More painting and priming
[December 22, 2009][0.75 Hours] Canopy and rollbar work
[December 24, 2009][1 Hour] Riveted Canopy Frame
[December 25, 2009][2 Hours] Finished installing rollbar
[December 26, 2009][2 Hours] Started empennage fairing
[December 27, 2009][4.5 Hours] Fiberglass work on empennage fairing painted stuff
[December 28, 2009][4 Hours] Emp. fairing elevator trim servo
[January 3, 2010][3.5 Hours] Worked on emp. fairing
[January 4, 2010][2.5 Hours] Started installing rear window fairing work
[January 5, 2010][3 Hours] Finished rear window, emp. fairing, misc stuff
[January 6, 2010][3 Hours] Wired elevator trim tail light wiring more fairing work
[January 7, 2010][3 Hours] Rigged elevator pushrods
[January 9, 2010][0.5 Hours] Connected elevator pushrods
[January 11, 2010][2.5 Hours] Back to work on the empennage fairings
[January 12, 2010][0.5 Hours] More filling of aft end of empennage fairing
[January 13, 2010][0.5 Hours] More fairing glassin'
[January 15, 2010][2 Hours] Mounted left wing temporarily
[January 16, 2010][2.5 Hours] Ran pitot line in wing drilled pitot tube to mount
[January 19, 2010][2.5 Hours] Worked on wingtip landing lights
[January 20, 2010][2 Hours] landing/taxi lights
[January 22, 2010][4 Hours] Wingtip lights
[January 23, 2010][8 Hours] Wingtips landing lights emp fairing tail light
[January 24, 2010][1 Hour] Finished taillight mounting bracket primed emp fairing
[January 25, 2010][4 Hours] Wingtip hinges Nav Antenna Mounted Emp Fairing
[January 26, 2010][1.5 Hours] emp fairing misc
[January 28, 2010][2 Hours] Rudder bottom fairing
[January 30, 2010][1.5 Hours] Moved the wings to the airport + rudder tips + emp fairing
[January 31, 2010][4 Hours] Finished empennage fairing installed bottom rudder tip
[February 2, 2010][2 Hours] started top tips of rudder and vertical stablizer
[February 5, 2010][5 Hours] Empennage Tips
[February 8, 2010][2 Hours] Test Fit Seats, emp tips
[February 10, 2010][3 Hours] Started fiberglassing rudder tips
[February 11, 2010][3.5 Hours] Made seal for plenum rudder tips
[February 15, 2010][4 Hours] Plenum Seal glassing empennage
[February 16, 2010][1 Hour] Sanding and filling rudder tips
[March 20, 2010][7 Hours] Fuselage move prep
[March 21, 2010][5 Hours] Moved project to the hangar!
[March 28, 2010][6 Hours] Installed left wing pitot installed
[March 31, 2010][3 Hours] Rigged left aileron; pitot heat connected
[April 2, 2010][4 Hours] Mounted right wing and propeller
[April 3, 2010][2 Hours] Wired some of the right wing, rigged ailerons
[April 7, 2010][2 Hours] Fuel sensor wire routing OAT sensor wired
[April 13, 2010][1 Hour] Empennage Tips
[April 16, 2010][3 Hours] More empennage tip filler work
[April 17, 2010][1.5 Hours] Emp filling
[April 18, 2010][3 Hours] More emp filling
[April 21, 2010][2.5 Hours] Filled right elevator
[April 25, 2010][4.5 Hours] Primed horizontal stab tips
[April 26, 2010][2.5 Hours] Primed elevator tips
[May 11, 2010][2 Hours] Filling rudder/vertical stabilizer tips
[May 12, 2010][3.5 Hours] Hangar Organization Finished empennage tips!
[May 14, 2010][2.5 Hours] Installed Empennage
[May 15, 2010][2 Hours] Wired tail nav and strobe light
[May 24, 2010][0.5 Hours] Fiberglassed NAV antenna to wingtip
[May 25, 2010][2 Hours] Rudder pedal linkage torqued prop bolts
[May 27, 2010][6 Hours] Prop Bolts - Alternator - Trim Tab - Lights
[May 28, 2010][1 Hour] Painted rudder linkages and topcoated flap cover and seat backs
[May 29, 2010][11 Hours] Too much little stuff to list!
[May 30, 2010][4 Hours] Wingtip lights and trimming
[June 1, 2010][5 Hours] Aft wingtip modification
[June 2, 2010][1.5 Hours] Started on exterior cowl surface prep
[June 5, 2010][7 Hours] Tech inspection, started to mount spinner, worked on "the list"
[June 7, 2010][2 Hours] Top Cowl Exterior Finishing
[July 9, 2010][4 Hours] Top Cowl Prep
[July 13, 2010][2 Hours] Pinhole filling
[July 16, 2010][2.5 Hours] Top Cowl Finishing
[July 17, 2010][2 Hours] Top coated the top cowl
[July 19, 2010][5 Hours] Bottom cowl work
[July 20, 2010][4.5 Hours] Bottom cowl primed parts
[July 21, 2010][4.5 Hours] Day at the hangar
[July 28, 2010][2 Hours] Made a pre-oiler
[July 30, 2010][5 Hours] pre-oiled engine
[July 31, 2010][2 Hours] Fixed prop control bolt and removed emag wiring
[August 1, 2010][8 Hours] Readied the engine for first start.
[August 2, 2010][5 Hours] Wingtips and FIRST ENGINE START!
[August 4, 2010][3 Hours] Right wingtip work
[August 8, 2010][5 Hours] primed fwd skin, wingtips misc
[August 9, 2010][4 Hours] Riveted on forward skin. Installed Canopy.
[August 10, 2010][5 Hours] Installed Vents, Secured Fuel level wire, left wingtip lights
[August 11, 2010][4 Hours] Wingtip antennas wired, lower cowl fitted
[August 12, 2010][4 Hours] Worked on air intake neoprene adapters to plenum
[August 16, 2010][4 Hours] Upper Cowl, Canopy Latch, other misc stuff
[August 18, 2010][1.5 Hours] First Taxi Test!
[August 19, 2010][3 Hours] Pitot-Static-Transponder Check
[August 25, 2010][3 Hours] Finished painting interior panels
[August 27, 2010][5 Hours] Tracked Prop and ELT antenna
[August 28, 2010][5 Hours] Installed Interior
[August 29, 2010][8 Hours] Weight and Balance, preparing for final FAA inspection
[August 30, 2010][3 Hours] AIRWORTHY!
[September 1, 2010][2 Hours] Started to put the airplane back together
[September 2, 2010][2 Hours] Installed wing root fairings
[September 7, 2010][3 Hours] Installing Panels, ect..
[September 9, 2010][3 Hours] Calibrated Capacitive Fuel Senders
[October 14, 2010][2.5 Hours] Installed Canopy Weatherstrip
[October 23, 2010][3 Hours] Installing access panels...