Wing Kit Order
  [December 28, 2005]: Ordered Wings!
  [December 29, 2005]: Verfied Order
  [December 30, 2005]: Van's new pricing
  [January 14, 2006]: Received wing order confirmation
  [March 17, 2006]: Wings Shipped!
  [March 25, 2006]: Received Wings

Wing Kit Inventory [8 Hours]
  [September 2, 2006]: [3 Hours] Started inventory of wings
  [September 4, 2006]: [1 Hour] More Inventory
  [September 12, 2006]: [2 Hours] Started inventory on the hardware
  [September 13, 2006]: [2 Hours] Finished Inventory

Spars [29.5 Hours]
  [September 14, 2006]: [1 Hour] Inspected main spars
  [September 15, 2006]: [0.5 Hours] Marked spars
  [September 16, 2006]: [1 Hour] Started work on spar nutplates
  [September 17, 2006]: [2 Hours] Countersunk spar for all nutplate rivets
  [September 18, 2006]: [2 Hours] Installed fuel tank nutplates
  [October 12, 2006]: [1 Hour] Finished fuel tank nutplates
  [October 13, 2006]: [0.5 Hours] Redid some countersinks
  [October 13, 2006]: [4 Hours] Finished nutplating/countersinking spars, started tie down brackets
  [October 14, 2006]: [0.5 Hours] Tie down bracket fabrication
  [October 16, 2006]: [2 Hours] Right tie down bracket
  [October 17, 2006]: [3 Hours] Finished tie down bracket, started rear spar
  [October 18, 2006]: [0.5 Hours] Prep to cut rear spars
  [October 19, 2006]: [1 Hour] Trimmed rear spars
  [October 22, 2006]: [3 Hours] Finished doublers.
  [October 23, 2006]: [2 Hours] Prep parts for priming
  [October 25, 2006]: [0.5 Hours] More rear spar priming prep
  [October 26, 2006]: [2 Hours] Primed spar components
  [October 27, 2006]: [3 Hours] Finished front and rear spars

Wing [190.5 Hours]
  [October 28, 2006]: [3 Hours] Started rib deburring
  [October 30, 2006]: [0.5 Hours] More deburring
  [October 31, 2006]: [2 Hours] More deburring
  [November 1, 2006]: [3 Hours] Finished deburring ribs
  [November 2, 2006]: [1.5 Hours] Rib prep
  [November 3, 2006]: [2.5 Hours] Finished flanging ribs, started fluting 'em
  [November 4, 2006]: [2.5 Hours] Finished rib prep, started assembly
  [November 5, 2006]: [2.5 Hours] Match drilling ribs
  [November 6, 2006]: [1.5 Hours] Conduit Holes
  [November 7, 2006]: [0.75 Hours] Finished conduit holes
  [November 8, 2006]: Wing wiring ideas
  [November 9, 2006]: [3 Hours] Prepping ribs for priming
  [November 10, 2006]: [4 Hours] Primed ribs
  [November 12, 2006]: Wing jig construction
  [November 13, 2006]: More work on the wing jig
  [November 15, 2006]: Finished wing jig
  [November 17, 2006]: [7 Hours] Riveted main ribs to spars
  [November 18, 2006]: Garage is COLD...BRRRR
  [November 19, 2006]: [1 Hour] Wings got jacked; Marked wing walk doublers
  [November 20, 2006]: [3 Hours] Match drilled left wing walk doubler, clecoed top left skin on, and more brackets
  [November 21, 2006]: [3 Hours] Match drilled left top skins, clecoed right skin on
  [November 22, 2006]: [1 Hour] Finished brackets for right wing
  [November 24, 2006]: [0.5 Hours] Detwisted right wing, clecoed on left wing bottom skin
  [November 25, 2006]: More right wing leveling
  [November 26, 2006]: [3 Hours] Match drilled rest of wing skins
  [November 27, 2006]: [3 Hours] Right leading edge
  [November 28, 2006]: [3.5 Hours] Leading edge work
  [November 29, 2006]: [2 Hours] Finished prep work on leading edges
  [December 28, 2006]: [4 Hours] Deburred Leading edge
  [December 29, 2006]: [3 Hours] Deburred left LE and prepped all LE for priming
  [December 30, 2006]: [4 Hours] Primed and dimpled leading edge parts
  [January 12, 2007]: [0.5 Hours] Prepped inboard leading edge rib and joiner
  [January 13, 2007]: [2 Hours] Riveted nutplates to joiner; clecoed LE
  [January 20, 2007]: [1 Hour] Started riveting right leading edge
  [January 22, 2007]: [2.5 Hours] FINISHED LEADING EDGES
  [January 24, 2007]: [2.5 Hours] Pitot tube mount
  [January 26, 2007]: [3 Hours] Started top skin prep - scarf joint
  [January 27, 2007]: [6.5 Hours] More skin prep - primed skins.
  [January 29, 2007]: [2 Hours] Finished deburring skeleton; fixed access plate countersink
  [January 30, 2007]: [1.75 Hours] Countersunk right spar
  [January 31, 2007]: [0.75 Hours] More spar countersinking
  [February 1, 2007]: [1 Hour] Finished spar countersinking, started dimpling ribs
  [February 5, 2007]: [1 Hour] Finished rib dimpling.
  [February 6, 2007]: [3 Hours] Finished spar/rib prep
  [February 7, 2007]: [1.25 Hours] Started riveting on right leading edge
  [February 8, 2007]: [2 Hours] Installed right leading edge, Test fit right tank
  [February 9, 2007]: [2.5 Hours] Right skins edge finishing and dimpling
  [February 10, 2007]: [6 Hours] Started riveting on right top skin; left leading edge
  [February 11, 2007]: [3 Hours] Prepped left top skins
  [February 13, 2007]: [1 Hour] Worked on right tank fitting
  [February 14, 2007]: [2.5 Hours] Finished fitting tanks
  [February 15, 2007]: [1 Hour] Tried to level left wing
  [February 16, 2007]: [4 Hours] Finished right wing top skin; fixed left wing twist
  [February 17, 2007]: Built wing cradle
  [February 18, 2007]: [1 Hour] Leveled/detwisted left wing
  [February 19, 2007]: [5.5 Hours] Finished left wing top skin
  [February 23, 2007]: Removed wing jig
  [February 24, 2007]: [2 Hours] Started aileron brackets
  [February 25, 2007]: [2.5 Hours] Aileron bracket/brace, flap brace drilling and deburring
  [February 27, 2007]: [2 Hours] Deburred brackets and braces
  [February 28, 2007]: [2.5 Hours] Prepped and primed brackets and braces
  [March 1, 2007]: [2 Hours] Riveted aileron brackets
  [March 2, 2007]: [2 Hours] Rivets aileron brace; Bottom skin pitot cutout
  [March 3, 2007]: [4 Hours] Deburred bottom skins
  [March 12, 2007]: Wings Inspected
  [March 27, 2007]: [3 Hours] Started pushrods
  [March 28, 2007]: [3 Hours] Pushrod work
  [March 29, 2007]: [1.5 Hours] Prepped pushrods and bottom skins for priming
  [March 30, 2007]: [4 Hours] Primed bottom skins; finished pushrods
  [March 31, 2007]: [4 Hours] Dimpled bottom skins
  [April 5, 2007]: [2 Hours] Drilled and countersunk flap brace
  [April 6, 2007]: [2 Hours] Riveted flap brace, prosealed conduit
  [April 9, 2007]: [1.5 Hours] Started riveting right bottom inboard skin
  [April 10, 2007]: [2.5 Hours] Finished bottom right inboard skin, started outboard
  [April 11, 2007]: [2.5 Hours] Finished right wing!
  [April 20, 2007]: Heated pitot tube arrived
  [April 26, 2007]: [0.5 Hours] Heated pitot testing
  [April 28, 2007]: [0.5 Hours] Pitot tube routing research
  [April 30, 2007]: [2 Hours] Started left bottom inboard skin
  [May 2, 2007]: [2 Hours] Finished riveting left bottom inboard skin
  [May 3, 2007]: [2 Hours] Working on bellcrank bushings and pitot tube routing
  [May 4, 2007]: [2 Hours] Finished pitot tube installation tasks
  [June 13, 2007]: [2.5 Hours] Finished riveting left bottom skins
  [June 20, 2007]: [1 Hour] Installed left aileron bellcrank
  [June 21, 2007]: [1.5 Hours] Installed left aileron
  [September 18, 2007]: [6 Hours] Aligned left aileron; mounted flap
  [October 9, 2007]: [4 Hours] Mounted right flap/Aileron - FINISHED WINGS!
  [March 17, 2008]: [1.5 Hours] Installed nutplates for inspection panels

Fuel Tanks [114.25 Hours]
  [November 30, 2006]: [2 Hours] Started right wing Z brackets
  [December 1, 2006]: [8 Hours] Finished right z-brackets. Got right tank on.
  [December 2, 2006]: [3 Hours] Right tank match drilling. Worked on angle attachment
  [December 5, 2006]: [2 Hours] Left tank Z-brackets
  [December 7, 2006]: New drill press
  [December 8, 2006]: [1 Hour] More left z-bracket work
  [December 9, 2006]: [1 Hour] Finished left z-brackets
  [December 10, 2006]: [3 Hours] Left tank work
  [December 11, 2006]: [2.5 Hours] Left tank match drilling, started angle attatchment
  [December 12, 2006]: [2 Hours] Misc tank work
  [December 13, 2006]: [1.75 Hours] Finished Stiffeners, started capacitive fuel sensor
  [December 16, 2006]: [3 Hours] Capacitive senders, access hole
  [December 17, 2006]: [4 Hours] Anti-rotation bracket, access panel work
  [December 18, 2006]: [2 Hours] Fuel cap / Drain drilling
  [December 21, 2006]: [0.25 Hours] Finished tank prep
  [December 22, 2006]: [4 Hours] Deburred Tank Parts
  [December 23, 2006]: [5 Hours] Skin Prep
  [December 26, 2006]: [2 Hours] Final preps before sealing
  [December 27, 2006]: [5 Hours] Riveted stiffeners for both tanks
  [December 28, 2006]: [3 Hours] Riveted gas cap and fuel drain
  [December 29, 2006]: [1.5 Hours] Deburred baffels, prepped z-brackets for priming
  [December 30, 2006]: [3.5 Hours] Primed z-brackets, cleaned parts, riveted my first rib
  [January 2, 2007]: [3.5 Hours] Riveted two more ribs on right tank
  [January 3, 2007]: [2.5 Hours] Another interior rib down on the right tank.
  [January 4, 2007]: [2.75 Hours] Riveted last interior rib on right tank. Prepped left tank
  [January 5, 2007]: [5.25 Hours] Riveted 3 interior ribs on left tank
  [January 6, 2007]: [8.5 Hours] Finished left tank interior ribs. Misc work on right tank.
  [January 7, 2007]: [3 Hours] Misc work on left tank. Resealed iffy spots.
  [January 8, 2007]: [1 Hour] Misc tank prep
  [January 9, 2007]: [5 Hours] Sealed inboard and outboard ribs on right tank
  [January 10, 2007]: [2 Hours] Right tank capacitive fuel sender
  [January 11, 2007]: [1.5 Hours] Access Panels; finished capacitive sender on right tank
  [January 12, 2007]: [2.5 Hours] Riveted left inboard rib
  [January 13, 2007]: [2 Hours] Riveted left outboard rib.
  [January 14, 2007]: [1.5 Hours] Final prep before closing right tank
  [January 15, 2007]: [1 Hour] More prep on right tank
  [January 16, 2007]: [4 Hours] Installed right baffle
  [January 17, 2007]: [3 Hours] Finished right tank! Finished capacitive sender in left tank.
  [January 18, 2007]: [1.5 Hours] Leak tested right tank; Prep work on left
  [January 20, 2007]: [3.5 Hours] Installed left baffle
  [January 24, 2007]: [0.5 Hours] Finished left tank!
  [January 25, 2007]: [0.25 Hours] Started leak test on left tank
  [January 27, 2007]: Finished Fuel Tanks!

Ailerons [33.5 Hours]
  [March 3, 2007]: [0.5 Hours] Aileron Stiffeners
  [March 4, 2007]: [4 Hours] Finished fabricating stiffeners, deburred skins
  [March 5, 2007]: [3 Hours] Primed stiffeners and skins
  [March 6, 2007]: [4 Hours] Riveted stiffeners
  [March 7, 2007]: [2 Hours] Assembled left aileron
  [March 9, 2007]: [6 Hours] Assembled right aileron; counterweight prep
  [March 10, 2007]: [6 Hours] Prep for priming
  [March 11, 2007]: [6 Hours] Primed; started assembly
  [March 13, 2007]: [2 Hours] Finished Ailerons

Flaps [29 Hours]
  [March 13, 2007]: [2 Hours] Prepped skeleton; clecoed on bottom ski
  [March 14, 2007]: [2.5 Hours] Shims, Skins and Hinges
  [March 15, 2007]: [1.5 Hours] Fabricated Angle, match drilled top skin
  [March 19, 2007]: [3 Hours] Bent FL-706B, lots of drilling and countersinking
  [March 20, 2007]: [2.5 Hours] Deburred flap parts
  [March 21, 2007]: [2 Hours] Prepped parts for priming.
  [March 22, 2007]: [1.5 Hours] Primed parts
  [March 23, 2007]: [2.5 Hours] Started flap assembly
  [March 24, 2007]: [5 Hours] Left flap assembly
  [March 25, 2007]: [3 Hours] Finished left flap
  [March 26, 2007]: [3.5 Hours] Finished right flap!

Wingtips [15 Hours]
  [March 29, 2008]: [6 Hours] Started left wingtip
  [March 30, 2008]: [7 Hours] Completed right wingtip, started lens
  [April 2, 2008]: [2 Hours] Finished lenses